|
CHAPTER II
CONSTRUCTION
AND FITMENTS OF PRESSURE VESSELS
12.
Design Code
-
vessels shall be
designed, constructed and tested in accordance with the
Indian standard 2825, as amended from time to time or
such other standard or code approved by the chief
controller.
-
A test and inspection
certificate issued by the manufacturer of the vessel
duly countersigned by an inspector that the vessel meets
with the requirements of the standard or code referred
to in sub-rule (1) shall be furnished to the chief
controller.
13.
Design Pressure
The design pressure of
vessel shall not be less than: -
-
The vapour pressure of
the gas in the vessel at 55d c if the vessel is meant
for the storage of liquefiable gases : Provided that if
the vessel is insulated the vapour pressure of the gas
in the vessel shall correspond to the maximum
temperature that is likely to be attained by the gas in
the vessel;
-
The developed pressure
of the gas in the vessel at 55dc if the vessel is meant
for the storage of a permanent gas.
14.
Design Of Vessels for Gases At Low Temperature
-
Refrigerated vessels: -
-
Vessels used for
storage of refrigerated gases shall be designed in
accordance with low temperature requirements under the
design code referred to in sub-rule (1) of rule 12.
-
The capacity of the
refrigeration system shall be adequate to maintain the
gas in the vessel at a temperature so that its vapour
pressure does not exceed the design pressure of the
vessel and shall also remain below the pressure
setting of the relief value on the vessel.
-
Insulated
vessels :-
-
The shell of the
vessel and its manhole nozzle shall be insulated with
a material approved by the chief controller. The
entire insulation shall be covered with a metal jacket
of a thickness not less than 3 mm. nominal and flashed
all openings so as to be weather tight.
-
The insulation shall
be of sufficient thickness so that the thermal
conductance at 15dc (expressed in calories or sq. cm.
per hour per limit prescribed by the chief controller.
15.
Filling Capacity And Filling Pressure.
-
The maximum quantity
of liquefiable gas filled into any vessel shall be
limited to the filling density of the gas and shall be
such that the vessel shall not be liquid-full due to
expansion of the contents with rise of the temperature
to 55dc. If vessel is uninstalled or to the highest
temperature, which the contents are likely to reach in
service if, the vessel is refrigerated or insulated. The
requirement shall be applicable irrespective of the
ambient temperature of the product at the time of
filling.
-
No vessel shall be
filled with any permanent gas in excess of its design
pressure
16.
Markings On Pressure Vessels
Every vessel shall have a
metal plate permanently fixed to it showing the following
particulars which shall be visible from the ground level
namely :-
-
Manufacturer’s
name and identification marks;
-
The standard
or code to which the vessel is constructed
-
Official stamp of
the inspector;
-
Design
pressure in kg/cm2
-
Date of initial
hydrostatic test and the subsequent test;
-
Hydrostatic
test pressure in kg/cm2;
-
Water capacity in
litres;
-
Gas capacity, if
filled with liquefiable gas ; and
-
Name or chemical
symbol of the gas for which the vessel is to be used.
17.
Painting Of Vessels.
Vessels shall be
adequately painted externally to prevent corrosion and shall
have a reflecting surface.
18.
Fittings
-
General :-
-
Fittings .- Each
vessels shall be provided with each of the following
fittings all of which should be suitable for use
with the gas at pressures not less than the design
pressure of the vessel to which they are fitted and
for temperature appropriate to the characteristics
of the gas and operating conditions namely
-
Pressure relief valve connected to the vapour space;
-
Drains;
-
Contents gauge or maximum level indicator;
-
Pressure gauge connected to the vapour space;
-
Means of measuring the temperature of the contents of the
vessel.
-
Vessel connection. –
Connections of vessels shall be designed and attached
to the vessel to the vessel in accordance with the
design code referred to in rule 12.
-
Pressure
relief :-
-
Every shall be
provided with two or more pressure relieving devices
in accordance with the provisions of the design code
referred to in rule 12;
-
The relief valves
shall be spring loaded and shall be set-to-discharge
and reach full flow conditions as required by the
design code referred to in rule 12;
-
Weight loaded relief
valves shall not be permitted;
-
The relief valves be
so designed that they cannot be inadvertently loaded
beyond the set pressure;
-
The design of the
valves shall be such that the breakage of any part
will not obstruct free discharge of the liquid under
pressure;
-
Safety relief valves
on any vessel shall be set to start-to-discharge at a
pressure not in excess of 110 percent of the design
pressure of the vessel and shall have a total
relieving capacity sufficient to prevent the
maximum pressure in the vessel of more than 120
percent of the design pressure;
-
Each safety relief
valve shall be plainly and permanently marked with
(the pressure in kg/cm2) at which it is set to
discharge with the actual rate of discharge of the
device in cubic meters per minute of the gas at 15dc
and at atmospheric pressure and with the
manufacturer’s name.the rated discharge capacity of
the device shall be determined at a pressure of 120
percent of the design pressure of the vessel;
-
Connections of
safety relief devices shall be of sufficient size to
provide the required rate of discharge through the
safety relief valves;
-
Safety relief valves
shall be so arranged that the possibility of tampering
is minimized and if the pressure setting or adjustment
is external the safety relief valve shall be provided
with suitable means of sealing adjustment;
-
Each safety valve
shall be provided with shut-off valve between it and
the vessel. The arrangement of the shut-off valve
installed between the relief valve and the vessel
shall be so designed as to afford full required
capacity flow through at least one of the safety
relief valves;
-
Safety relief valves
shall have direct communications with the vapour space
of the vessel;
-
For vessels other
than those mounted on the vehicles of over 4500 litres
water capacity relief valves shall be fitted with
extended vent pipes adequately supported and having
outlets at least 2 meters above the top of the vessel
and at least 3.5 meters above the ground level and the
vent pipes shall be fitted with loose-fitting rain
caps;
-
Relief valves shall
be tested by a competent person for correct operation
not less than once in a year and a record of such test
shall be maintained the test certificate shall be
issued in the prescribed proforma.
-
Shut-off and emergency shut-off valves :-
-
all liquid and
vapour connections on vessels except those for relief
valves plugged openings and those where the connection
is not greater than 1.4 mm diameter opening shall have
shut-off valves located as close to the vessel as
practicable;
-
all liquid and
vapour connections on vessels except those for relief
valves and drainage connections of small diameter
shall have an emergency operated valve or a remotely
controlled flow valve. the emergency shut-off valve
referred to in clause (i) , unless the emergency
shut-off valve as a remotely controlled valve which
can be operated from a safe area and shall be of a
type which shall not fail :
-
where the emergency
shut-off valve is of the excess flow type its closing
rate of flow shall be below the rate, which is likely
to be experienced. excessflow valve shall a rated flow
capacity sufficiently above normal flow requirements
to prevent valve chatter.
-
Liquid level
gauging device :-
-
A vessel used for
liquefiable gas or dissolved gas shall be equipped
with a liquid level gaugine device to afford ready
determination of the amount of liquid in the vessel at
any time;
-
All liquid level
indicators shall be suitable for operation at the
design pressure of the vessel;
-
Every vessel shall
in addition,be equipped with a fixed maximum level
indicating device depending upon the liquefiable gas
or dissolved gas filled in the vessel;
-
Gauging devices that
require bleeding of the contents of the vessel such as
a rotary tube fixed tube and slip tube shall be
designed in such a manner that the same cannot be
completely withdrawn in normal gauging operations.
-
Pressure gauge
Every vessel shall be provided with at least one
pressure gauge.
19.
Periodic Testing Of Pressure Vessel In Service
-
All vessels shall be
hydraulically tested by a competent person at a pressure
marked on the vessel at intervals of not more than five
years after the date of first test provided that in the
case of vessels containing corrosive or toxic gases the
periodic test shall be done at an interval of two years.
In case of vessels which
are so designed constructed or supported that they cannot
be safely filled with water or liquids for hydraulic
testing or which are used in services where traces of
water cannot be tolerated Chief Controller may permit
pneumatic testing along with non-destructive tests instead
of hydraulic testing as per procedure laid down in vessels
fabrication code; after satisfying himself about the
adequacy of the safety precautions undertaken.
-
The competent person carrying out
the test as required under sub-rule (1) shall issue a
certificate of test in prescribed proforma.
20.
Precautions to be observed in carrying out hydraulic test.
in carrying out the
hydraulic test referred to in rule 19 the following
precautions shall be observed namely :-
-
Before the test is
carried out each pressure vessel shall be thoroughly
cleaned and examined externally and as far as
practicable internally also for surface defect corrosion
and foreign matter. During the process of cleaning and
removal of sludge if any all due precautions shall be
taken against fire or explosion if such sludge is of
pyropheric nature or contains spontaneously combustible
chemicals;
-
As soon as the test is
completed the vessel shall be thoroughly dried
internally and shall be clearly stamped with the marks
and figures indicating the person by whom test has been
carried out and the date of test and a record shall be
kept of all such tests;
-
Any vessel, which
fails to pass the hydraulic test, or which for any other
reason is found to be unsafe for use shall be destroyed
or rendered unsuitable under intimation to the chief
controller
|